News Flash Home
The original item was published from 4/2/2014 1:28:00 PM to 4/8/2014 3:50:00 PM.

News Flash

Construction Updates

Posted on: April 2, 2014

[ARCHIVED] Sahuarita Road Construction Update – Tuesday 04/01/14

This is the April 1, 2014 construction update for the Sahuarita Road Phase II Project.

This week, within the Segment 2A and 2B Projects, crews will continue painting the new Santa Cruz River bridge structure (weather permitting) and also finalize the new Sahuarita Road landscape irrigation system. Both new Sahuarita Road bridges at the Santa Cruz River are open to vehicular traffic. Final paving (with rubberized asphalt) was installed the last week of March, 2014. Next week, an asphalt seal coat will be applied to the intersection of La Villita Road/Sahuarita Road which will make way for temporary and final pavement markings. Other remaining work includes the installation of pedestrian safety railing on the westbound bridge - and as such the westbound bridge sidewalk is closed until completion. Pedestrians should use the eastbound bridge as an alternative route. Work along the realigned Nogales Highway will pause for a few weeks until the planting of new landscaping begins later this spring.

The Segment 2C Project, is the final portion of the Sahuarita Road Phase II project between Nogales Highway and the Eastern Town Limits (just west of Country Club Road). Ongoing work in this area includes relocation of existing utilities, an outlet extension on the existing concrete box culvert (west of Delgado Road), and the hauling/placement of fill material within the new Sahuarita Road eastbound lanes. As part of the earthwork haul, drivers should be aware of large trucks entering and exiting Sahuarita Road between Nogales Highway and Santa Rita Road. In the area between Santa Rita Road and Delgado Road a temporary construction zone lane shift is being constructed. Upon completion of this temporary pavement, traffic lanes will be shifted to the northern portion of the roadway to open up additional construction areas within the future eastbound lanes.

As part of the ongoing construction efforts, drivers should be aware of all traffic control devices/signage and all speed limit reductions, as large equipment may be working near the roadways.

A summary of the anticipated short-term (2-3 week) construction activities can be seen in the April 1, 2014 Look Ahead Schedule

Facebook Twitter Email